Tractor PTO (Power Take-Off) Inspection Checklist
No.PTO-2026-021
Document title identifying the PTO inspection checklist.
1. General Information
Record the inspection date and inspector name.
| Inspection date | 7/14/2026 |
2. Object of Inspection
Identify the tractor by name and operating hours.
| Object name | John Deere 8R 410 | Operating Hours, hours | 3200 |
3. Visual Inspection
Check PTO shaft condition, guard presence and condition, and connection security.
| Shaft Condition | Good | Guard Present | ☐ |
| Guard Condition | Good | Connections Secure | ☐ |
4. Operational Test
Test PTO engagement and disengagement smoothness, and check for abnormal noise or vibration.
| ☐ Engagement Smooth | ☐ Disengagement Smooth |
| Noise and Vibration: None |
5. Defects
List any defects found during visual inspection or operational test.
| No. | Damage description | Photos |
|---|---|---|
| 1 | - | not filled in |
| 2 | - | not filled in |
6. Additional Information
Record any additional notes or observations.
| Identification was carried out | Tractor ID: TR-2021-078 |
| There are remarks | PTO system inspected. Guard present and secure. Operation smooth. |
7. Inspection Participants
List the technician and farm manager involved.
| No. | Full name | Position / status | Comment |
|---|---|---|---|
| 1 | David Miller | Operator | Performed PTO inspection. |
| 2 | James Whitfield | Farm Manager | Witnessed test. |
Signatures
Capture signatures of the inspector and manager.