Pump Inspection Checklist
No.PIC-2026-021
1. General Information
| Inspection date | 7/14/2026 | Address | Pump Station 3, Water Treatment Plant, 1500 River Road, Denver, CO 80201 |
2. Object of Inspection
| Object type | not filled in | Object name | Centrifugal Pump - P-301 |
| Technical condition | not filled in | Operating Hours, hours | 5000 |
| Release date | 1/10/2023 | Start of operation | 2/1/2023 |
3. Main Parameters
| Visual Condition | Good | Leaks Observed | ☐ |
| Corrosion Observed | ☐ | Cracks Observed | ☐ |
4. Additional Parameters
| Operational Status: Operational | Vibration Level: Normal |
| Noise Level: Normal | Temperature: 42 |
| Pressure: 4.5 | Flow Rate: 120 |
5. Defects Found
| No. | Damage description | Photos |
|---|---|---|
| 1 | - | not filled in |
6. Additional Information
| Identification was carried out | Pump ID: P-301 |
| There are remarks | All checks passed. Minor wear noted on coupling. |
7. Inspection Participants
| No. | Full name | Position / status | Comment |
|---|---|---|---|
| 1 | Kevin Brown | Maintenance Technician | Performed inspection. |
| 2 | Nancy Davis | Maintenance Supervisor | Reviewed and approved. |