Gas Boiler House Inspection Report
No.GBH-2026-0714
1. General Information
| Inspection date | 7/14/2026 | Address | 45 Maple Avenue, Manchester M1 2AB |
2. Object of Inspection
| Object name | Main Boiler House, Building B | Technical condition | not filled in |
3. Boiler House Environment
| Ventilation Adequate | ☐ | Gas Detection Present | ☐ |
| General Condition | Satisfactory |
4. Boilers and Systems
| Boiler 1 Condition: Good | Boiler 2 Condition: Fair |
| Pipework Condition: Fair | Safety Valve Condition: Functional |
| Pressure Gauge Condition: Good | Emergency Shutoff Test: Pass |
5. Defects
| No. | Damage description | Photos |
|---|---|---|
| 1 | - | not filled in |
| 2 | - | not filled in |
6. Additional Information
| Identification was carried out | Boiler house identified as Main Boiler House, Building B |
| There are remarks | Overall condition satisfactory. Minor corrosion on pipework near Boiler 2. |
7. Inspection Participants
| No. | Full name | Position / status | Comment |
|---|---|---|---|
| 1 | James Carter | Inspector | Gas Safe registered engineer |
| 2 | Sarah Thompson | Facility Manager | Building B facility manager |