Energy Facility Technical Condition Assessment
No.EFTA-2026-0012
1. General Information
| Inspection date | 7/14/2026 | Address | Riverside Power Station, 1 Power Plant Road, Portland, OR 97201 |
| Basis for inspection | Periodic asset management review |
2. Object of Inspection
| Object name | Riverside Power Station | Technical condition | not filled in |
| Release date | 1/1/2005 |
3. Main Parameters
| Overall Condition Rating | Fair | Remaining Life Estimate | 12 |
| Construction Year | 2005 |
4. Key Findings
| No. | Damage description | Photos |
|---|---|---|
| 1 | - | not filled in |
| 2 | - | not filled in |
5. Additional Information
| Identification was carried out | Riverside Power Station - Main turbine hall |
| There are remarks | Overall condition rated Fair. Remaining life estimated at 12 years. Key investments needed in cooling tower and control system. |
6. Inspection Participants
| No. | Full name | Position / status | Comment |
|---|---|---|---|
| 1 | Dr. Alan Grant | Senior Engineer | Lead assessor |
| 2 | Jennifer Lopez | Asset Manager | Received assessment |